| No |
Professional experiences |
Start Year |
End Year |
1 |
Project manager of installation Italian Nouyvallencia equipment for yazd Polyester co. |
2001 |
2002 |
2 |
Project manager of installation project of Inspection organization of Iran |
1999 |
2001 |
3 |
Project manager of new acrylic project in poly acryl |
1999 |
2000 |
4 |
Project manager of erection for steel structure of Azarbaijan steel complex. |
1999 |
2000 |
5 |
Project manager of installation of Khuzestan cement equipment |
1995 |
1997 |
6 |
Project manager of 214-house building for Sharif university. |
1993 |
1994 |
7 |
Project manager of installation of cement equipment for Khuzestan cement company. |
1993 |
1995 |
8 |
Project manager of installation of 5 clinker silos |
1993 |
1994 |
9 |
Project manager of concrete structure of library of Marashy Najafi Qoum |
1990 |
1992 |
10 |
Project manager of concrete structure of university of Mofid, Qoum |
1989 |
1991 |
11 |
Project manager of concrete structure of Ya mahdi (for Sepah) |
1988 |
1990 |
12 |
Project manager of 5 story concrete building for industry of defense |
1988 |
1989 |
13 |
Project manager of concrete foundation of Rajaee power plant |
1986 |
1987 |
14 |
Site manager of concrete water tanks in Shiraz (51000 m3) |
1982 |
1984 |
15 |
Site Manager of Hamedanian Hospital in Esfahan and 40 house buildings unit forits personnel. |
1980 |
1982 |
16 |
Civil Manager of execution of Channels in Almeghdayeh Iraq |
1978 |
1979 |